JPS net billing in Jamaica

What happens to solar electricity you do not use?

Net billing lets you sell spare solar electricity to JPS once your system is approved. The payment per unit is lower than the price you pay for electricity. Start by working out how much solar your home or business can use while the sun is out.

Checked 31 August 2026: the latest OUR notice available lists J$27.201/kWh for 2025 December. Export rates move monthly; always check the latest notice before relying on one figure.

What net billing means

Electricity you buy and sell is counted separately.

01

Your panels supply the house

Solar used while it is being generated reduces the electricity you need to buy from JPS Jamaica.

02

Surplus goes to the grid

An approved meter records electricity exported under the Standard Offer Contract.

03

Buying and selling use different rates

You buy imported electricity at the applicable retail tariff and receive the lower OUR-approved rate for exports.

The export price is the short-term variable avoided cost of generation plus a 15% renewable-energy premium. It mainly follows fuel-generation cost, so it changes. It is not the full residential price shown on your JPS bill.

For 100 kWh in the worked example above: using it in the home avoids about J$7,596; exporting it earns about J$2,720. That J$4,876 gap is why system size and daytime use matter.

Official 2025 export rates

The rate moved from J$19.17 to J$29.23.

Latest publishedJ$27.201/kWh2025 December

These are the monthly net-billing energy rates in the OUR notice issued 3 February 2026. November and December were unusually high relative to the rest of the year, so using the latest number as a long-term forecast would be optimistic.

J$/kWh, short-term avoided cost plus 15%. Source: Office of Utilities Regulation.
Show the rate table
MonthJ$/kWhMonthJ$/kWh
January 202520.154July 202519.979
February 202520.243August 202521.290
March 202521.077September 202522.176
April 202522.911October 202522.090
May 202521.122November 202529.233
June 202519.171December 202527.201

Is it worth doing?

Usually useful. Rarely the main reason to buy solar.

Best case

You already have daytime demand

Air conditioning, water pumping, a home office or business loads can absorb solar directly. Net billing catches the genuine surplus.

Watch this

Your house is quiet all day

A large array may export much of its output at the lower rate. Ask for the quote to show self-use and exports separately.

Do not assume

More panels mean better payback

The 10 kW residential limit is a ceiling, not a target. The best financial size can be smaller.

A battery changes timing, not the export rule. It may raise self-consumption and provide backup during outages, but its cost can lengthen payback. Ask to see the quote with and without a battery.

Before an application

Four checks before paying a deposit.

Open the BSJ consumer-information page and current approved-inverter list →

Application process

The paperwork comes before permission to export.

  1. 1

    Prepare the Ministry application

    Use Application Form v2.0. The applicant details should correspond to the JPS tax invoice, and the facility address must include the city and parish.

  2. 2

    Build the technical pack

    Include a certified single-line drawing, JPS invoice no more than three months old, BSJ inverter listing and certificate, and an itemised bill of quantities/specifications.

  3. 3

    Build the legal pack

    Expect government ID and evidence of ownership or permission to use the property. Address differences, unregistered possession, leases, companies, charities or caveats need additional documents.

  4. 4

    Pass the preliminary review and pay the processing fee

    The Ministry’s current instruction sheet quotes a non-refundable J$19,000 processing fee. Follow the Ministry’s payment instruction after it has checked the submission.

  5. 5

    Receive the licence and JPS contract

    After approval and the additional per-kW fee, the licence is issued. The 2022 regulations say JPS has 30 days after receiving it to issue the OUR-approved Standard Offer Contract.

  6. 6

    Construct, inspect and commission

    The completed installation needs inspection and certification. Written notice, the applicable one-time use-of-system charge and JPS commissioning follow before legal export begins.

Do not energise an export connection early. The Ministry application form says applicants must not connect to or export energy to the grid without written approval from JPS Jamaica.

Fees and uncertainty

There is a published fee mismatch.

Processing fee

J$19,000Non-refundable; Ministry instruction sheet.

Per-kW fee in current sheet

J$1,800/kWBased on permitted excess capacity.

Per-kW fee in linked Gazette

J$1,500/kWThe Ministry still links the 2017 notice.

The Ministry’s instruction sheet and the Gazette notice on the same official document page do not agree. We have shown both instead of choosing one. Confirm the amount and payment instructions directly with MSETT before paying.

These figures also exclude the drawing, inspection, any design changes, JPS use-of-system charge and installer administration. Ask a quotation to identify each of those separately.

The residential solar tax credit is a separate process. Published TAJ criteria require certification by a licensed electrical inspector, but do not list a net-billing licence as a condition. Do not let an installer use the tax credit to rush you into an export arrangement you do not need.

Questions for an installer

Get the net-billing promise in writing.

Read the full Jamaican installer checklist →

Short answers

Jamaica net-billing questions.

What is the current JPS net-billing rate?

The latest OUR notice available when this page was checked lists J$27.201/kWh for 2025 December. The export rate varies monthly; the 2025 range was J$19.171 to J$29.233/kWh.

Is net billing the same as net metering?

No. Under net billing, imported and exported electricity are valued separately. Sending one kWh to the grid does not cancel one imported kWh at the retail price.

How large can a residential system be?

The Ministry’s requirements say no more than 10 kW for a residential system. That is a maximum, not a recommendation.

How long does approval take?

There is no honest single end-to-end time to quote. The 2022 regulations give JPS 30 days to issue a Standard Offer Contract after receiving the licence, but document preparation, Ministry review, construction, inspection and commissioning are separate stages.

Can I connect now and finish the paperwork later?

Not for grid export. The current application form explicitly says not to connect to or export to the grid without written JPS approval. Discuss any non-export or isolated design with the responsible licensed electrical professional.

Primary sources

What this guide was checked against.

Last fact-check: 31 August 2026. This is an independent practical guide, not legal advice or a substitute for instructions from MSETT, JPS Jamaica, OUR, BSJ or a licensed electrical professional.